Preparations before starting the Biomass Pellet Machine

1. Check whether the gearbox internal machine (gear) oil is sufficient;

2. Whether there is lubricating oil in each lubricating bearing part;

3. There is organic oil in the oil cup;

4. Whether there are wood blocks, stones and other sundries in the granulation room;

5. Whether there are iron blocks, iron wires, etc. on the magnet

6. Whether the wires in the control cabinet are broken, damaged, discolored, whether the electrical components and terminals are loose, and whether the voltage is normal.

Boot sequence:

1. Start the main motor, wait for the step-down to start normally, start the forced feeding, open the front oil inlet plate, start the speed-adjusting hinge after 2-4 minutes of oiling, and adjust the frequency of the speed-regulating hinge to 6HZ, see The operation of the biomass pellet machine, if it is running normally, wait another 2 minutes and adjust to 8HZ to see the operation of the biomass pellet machine, and gradually increase it. The current value of the main engine (200A-240A) cannot be lower than 180A, nor higher than 240A ;

2. The operator cannot leave the electric control cabinet at will in order to adjust the current at any time. When the moisture content of the raw material is high, the electrorheological pointer will go down. At this time, the current pointer should be adjusted upward. When the moisture content of the raw material is low, the current The variable pointer will go up, at this time, the current should be adjusted downward, and the current should always be controlled below the rated current;

Shutdown sequence:

1. When shutting down, first stop the agitator in the raw material bin, then stop the speed-regulating auger, then open the feeding plate to add oil, let the main machine idle for 3-5 minutes, then turn off the forced feeder, and then turn off the main machine. The operation sequence is; the motor that is turned on first is turned off later, and the motor that is turned on later is turned off first.

2. Start-up sequence: main machine - forced feeding - speed-adjusting reamer - raw material bin agitator;

3. Shutdown sequence: raw material bin agitator - speed-adjusting reamer - forced feeding - main engine.
Share to:

LET'S GET IN TOUCH

We will contact you immediately

Fill in more information so that we can get in touch with you faster

Privacy statement: Your privacy is very important to Us. Our company promises not to disclose your personal information to any external company with out your explicit permission.

Send